Answers:


Definite estimate is also termed as bottom-up estimate. The accuracy of this estimate is much more as compared to the accuracy of the above two estimates. However, the time required to prepare such type of estimate is relatively more. In order to prepare a definite estimate, the project manager must take the help of work breakdown structure (WBS). A project manager requires a WBS for preparing a definite estimate because a project manager needs to account for the cost of each and every deliverable.